1. Project Overview
1, project name
Diene Phase II Project with an Annual Output of 200 Tons
2, construction site
Honghuatao Town, Yidu City.
3. Main construction content
Expand the capacity of the existing diene production line, and build a sewage treatment center with 1,200 square meters and 2 production lines.
4. Main products and scale
Diene (dienol ketone acetate, C23H32O3) 200 tons/year
2. The name and contact information of the construction unit of the construction project
1. Name of construction unit: Hubei Minsheng Biological Medicine Co., Ltd.
2. Contact address: Honghuatao Town, Yidu City
3, Contact: Mr. Peng 13508603937
3. The name and contact information of the environmental impact assessment agency undertaking the assessment
1. Environmental impact assessment agency undertaking the project: Hubei Tianliang Environmental Protection Technology Development Co., Ltd.
2, Contact address: No. 48, Shengli 4th Road, Yichang City
3. Contact: Liu Gong 0717-6445246
4, E-mail: ychbs20@163.com diene
Four. Working procedures, main work content and results submission methods of environmental impact assessment
1, work procedure
Collecting data, data analysis, site survey, investigation and analysis, environmental status assessment, environmental impact prediction and evaluation, comprehensive analysis, public participation, drawing conclusions, writing reports, expert review, and submitting to environmental protection authorities for approval.
2, work content
(1) Basic profile analysis of the project;
(2) Survey of the surrounding environment of the project;
(3) Monitoring and evaluation of the current status of atmospheric environment, acoustic and other environmental quality in the project construction area;
(4) Project engineering analysis;
(5) Pollution source analysis and pollution prevention and control measures during the project construction period;
(6) Pollution source analysis and pollution prevention and control measures during the project operation period;
(7) Determine the environmental quality standards and pollutant discharge standards according to the project area;
(8) Public participation;
(9) Environmental monitoring and environmental management;
(10) Project feasibility conclusion.
3. How to submit results
The environmental impact assessment will finally submit the results in the form of an environmental impact report.
5. Main items for public opinion
Public opinion consultation should take the form of online information disclosure, posting publicity, and issuing questionnaires. The survey objects mainly include residents in the surrounding areas of the project, enterprises and institutions. The main consultation opinions include:
(1) Do you understand the construction project?
(2) The approximate distance between your residence or workplace and the construction project?
(3) Are you satisfied with the environmental quality of the area where the construction project is located?
(4) If you are not satisfied, what do you think are the main environmental problems currently existing in the proposed area of the construction project?
(5) What do you think of the impact of the construction project on the surrounding environment?
(6) What do you think is the main environmental impact of the construction project after it is completed and put into production?
(7) What do you think is the main impact of the construction of the construction project on the local economy and society? Diene
(8) What is your attitude towards the construction of this construction project?
Six, the main way the public put forward opinions
Submit written opinions to the construction unit or its entrusted environmental impact assessment agency, and the environmental protection administrative department responsible for reviewing and approving the environmental impact report of the project by letter, telephone, e-mail or other methods required by the relevant announcement.